Fulcrum Construction Consultancy
Fulcrum ConstructionConsultancy

My Experience

Infrastructure

Siemens Trans Pennine Express Train Maintenance Facility, Ardwick, Manchester 

Contractor Project Manager responsible for tender preparation and subsequent delivery of £25m design and build project providing bespoke facilities for 50 new trains. The depot provides formula 1 type pit facilities including wheel lathes, engine/bogey drops, train washing, CET, cleaning, office and staff welfare facilities adjacent to the main line. Significant element was the closure of Manchester Piccadilly station for three weekends to effect major track and signalling works in 'the throat' to effect access to the new depot. Delivered under NEC.

 

Railtrack Ltd York

Construction Manager London NE Zone - Plain Line and S&C track renewals. Full management responsibility for possession planning and extensive track replacement and maintenance within fixed timescales in a live railway environment by framework contractors.

 

Docklands Light Railway, Beckton Extension

Contractor Section Engineer dleivery responsibility for heavy civils structures including, earthworks, piling, RC 130m span balanced cantilever bridge, 200m long PC concrete viaduct, structural steelwork and utility provision, part of project of £140m to construct 8km of elevated track and stations.

 

Hampton Water Treatment Works, Middlesex

Contractor Senior Engineer responsible for all aspects of engineering delivery of £22.5m scheme providing ozonation facility to live works. Heavy RC structures and pipelines including shafts and tunnels. Project included a series of successful 72 hour shutdowns of the works, and with it a third of London's water supply, to affect major connection works to the existing plant.

Education

Sheffield Hallam University, NEC4 Alliance

Initially coordinated WS1 design and cost plan for Phase 1 new builds of £80m whilst Alliance contract procured. Post award, led mobilisation phase, independently supporting all four alliance partners to collaboratively develop methods of working and interpretation of NEC4 Alliance contract. Drafted Alliance Protocol to capture this intent. Post mobilistion assumed role of Programme Alliance Manager, responsible to the Alliance Board acted as stratgeic lead for multiple schemes providing impartial direction and support to deliver Alliance intent.

 

University of Hull, Project Governance, Sponsorship and Delivery Protocols

Developed a series of delivery handbooks, protocols and template documents to establish a fully revised method of working for all UoH Estates Capital Delivery projects. Including, University project governance, business case planning, sposor/stakeholder enagagement and project managment delivery.

 

University of Hull, Academic Facilities Enhancement Programme

Client Programme Manager, supporting University Estates and Academics to deliver a 6 year programme of work to transform the academic facilities in line with academic aspirations and projected headcounts. Successfully developed overall delivery strategy for new build, refurbishment and demolition with third party consultant following extensive stakeholder enagement. Led briefing of University Leadership Team and gained approval for circa £100m programme of work. Initiated first phases of delivery.

 

University of York, Heslington East Campus

Client Project Director, responsible for leading all aspects of project delivery of the first phase of the £165m new campus through the entire project lifecycle. Included extensive stakeholder management, design briefing, consultant team management, design management, budget control, single and two stage contractor procurement, construction delivery and handover. This represented administration of approximately 20 different contracts including infrastructure, earthworks, in excess of 25,000m2 new build GIFA teaching/reserach space in five seprate buildings and extensive landscaping. Project used NEC extensively.

 

University of Manchester, Manchester Engineering Campus Development (MECD)

Client Project Director, responsible for leading the £350m new campus project through RIBA workstages 1 to 3. Included strategic project planning, extensive stakeholder management, design briefing, consultant team selection and management, cost management, determination of contractor procurement strategy and subsequent appointment of main contractor and key supply chain partners. 

 

BSF Sheffield

Main contractor Project Director, leading second stage tender for Taylor Woodrow successfully negotiating financial close with the LA. Post award implemented the design and construction of the first three of twenty plus secondary schools. Developed with the LA the New Project Approval Process for the LEP which was ultimately widely used on other BSF schemes.

Industrial

Portasilo Ltd. York 

Set up and managaged a self contained business unit carrying out a range of site functions associated with the supply, installation, commissioning and ongoing maintenance of equipment housings through a range of industries including telecoms, rail and power transmission. Role involved close liaison with factory, client, suppliers and operations staff to allow works to be completed whilst not compromising client operations.

Mixed Use

SoYo, Leeds

Design and project management support to Moda and Caddick Developments. Developed a multi party site interface document to address practicalities of delivering five seprate schemes in parallel on a congested city centre site. This included significant negotiation with contractors, third parties and funders to allow inclusion in contract documentation.

 

Little Peter Street, Manchester 

High Rise mixed use scheme. Design management of multi disciplinary team through WS2-3 for Buccleuch Property.

 

First Street North, Manchester 

Client Strategic Project Manager coordinating a joint venture project between MCC and Ask Developments. Scheme includes new theatre and cultural centre, 4* hotel, multi sorey car-park and retail/food outlets.

 

Diamond Island, Ho Chi Minh, Vietnam

Client Strategic Project Manager trouble shooting of a £100m mixed use scheme that was in serious construction programme difficulty for a Vietnamese developer.

 

Chester Theatre 

Client Project Manager assisting Cheshire West and Chester Council through RIBA stages A to D. Lead consultant ream selection, design development and contract procurement. Scheme includes a new build 800 seat theatre and refurbishment of existing 1932 Odeon cinema into a cultural centre with cinema, workshop space, library and restaurant facilities.

Residential

University of York, Goodricke College

Client Project Director responsible for design management, procurement and subsequent contract administration during construction of a £29m 620 bed student accommodation facility.

First Street, Manchester

Our Details

Fulcrum Construction Consultancy Limited

Company No.

10221056

VAT Reg No.

244685385

Correspondence Address

3, Florent Court, Regent Street, Pocklington

York

YO42 2PQ

Tel:

07826 859720 07826 859720

Email:

dan@fulcrum-construction-consultancy.co.uk

Our News

May 2020 Update

As the world deals with Covid 19 thankfully we have been able to continue working remotely at Sheffield Hallam as the NEC4 Programme Alliance Manager (PAM). With circa £80m of projects now launched, Alliance Partners SHU, BDP/Arup, CBRE and BAM Construction are progressing on a number of fronts from WS2 design through to the imminent launch of construction on the £14m Atrium Scheme.

 

As PAM we continue to provide independant strategic, process and contract support to the partners. Assisting them to deliver construction projects in a collaborative way, integrating the full delivery team from the start of a project as equal partners with a vested interest in successful project delivery.

 

We are also pleased to announce the completion of Kilnwick Pavilion for Pocklington Rugby Club. Just a shame Covid means it cannot be used!!!

Print | Sitemap
© Fulcrum Construction Consultancy